OurSwords / Project watch

The R132.
A changing route.
A clearer picture.

What is changing along the R132, from Estuary to Malahide Road — and what it means for driving, walking, cycling and buses.

● Under construction

Building the connections

Work continues at the junctions and along the walking and cycling routes.

Consultation
Complete
Approval
Granted
Construction
In progress
Completion
Not confirmed

The Estuary junction on the R132, photographed from the pedestrian bridge with traffic signals and construction areas visible.
The Estuary junction on the R132, photographed from the pedestrian bridge with traffic signals and construction areas visible. Photograph taken on 1 November 2026. © OurSwords.ie. Reuse requires permission.
≈3 kmScheme corridor
3 junctionsRoundabout conversions in the scheme
≈25 monthsEstimated construction from April 2026
20 Nov 2026Last editorial verification

The immediate picture

What to know now

Works programme: 13–27 November 2026.

Planned · 23 November, 10am

Seatown: prepare for changes to familiar turns

Seatown’s vehicle traffic signals are scheduled to start at 10am on Monday, 23 November 2026. Pedestrian and cyclist crossings at the junction remain closed; the council advises continued use of the Seatown Footbridge. Construction will continue for a number of weeks and drivers should expect some delays while adjusting. A new council leaflet explains the alternative northbound and southbound journeys from Old Seatown Road; see Your journey below.

Crews are finishing drainage and kerbs at Seatown, adjusting line markings at Estuary and surfacing cycle tracks at both junctions. Chapel Lane surfacing and footpath work continues. Temporary one-lane sections may operate outside peak hours, between 10am and 4pm, as required.

Bostik: the traffic signals beside the factory were reported operating by OurSwords’ owner on 13 November.

Local reaction

What people are saying

Councillor Luke Corkery says aspects of the new Estuary junction will be re-examined following reviews. He has called for the council to keep listening to people’s concerns.

Calls for a plan: Councillor Darren Jack Kelly says he joined residents protesting outside Fingal County Council’s offices and has called on the council to set out a clear plan to address their R132 concerns. He said he would raise them again with the council executive.

In the same discussion, one commenter on 11 November said they had left the car at home because walking was quicker.

Earlier public comments on the council’s October updates described severe queues and frustration with the Estuary layout.

One scheme, different milestones

Junction by junction

01 / ESTUARY
Signals operational

Open, with monitoring continuing

The lights began operating on 14 October. After early delays, the council adjusted the timings on 16 October and said traffic flow had improved.

Finishing work and monitoring continue at the junction.

Confirmed signal dates · 14 & 16 October 2026
Read the Estuary explainer →
02 / SEATOWN
Works in progress

Vehicle signals planned for Monday, 10am

Vehicle signals are scheduled for 10am on 23 November. Pedestrian and cycle crossings remain closed; continue using the Seatown Footbridge.

Footpath and cycle-track works continue around the junction.

Planned activation · 23 November 2026, 10am
03 / MALAHIDE ROAD
In the approved scheme

A further junction conversion

The roundabout beside Pavilions is one of the three junctions to be converted under the scheme.

The circular layout was still visible in our 1 November photographs.

Completion status · not verified

Original OurSwords photographs

Along the R132

Estuary, Seatown and the Malahide Road/Pavilions approaches, photographed on 1 November 2026. Tap a photograph to look closer.

Estuary: the junction and its approaches

Seatown, beside Woodies

Malahide Road and Pavilions

The dated record

How we got here

  1. Public consultation began

    The project entered public consultation.

  2. Planning application submitted

    Detailed proposals moved into the approval process.

  3. Planning approval granted

    An Bord Pleanála approved the scheme.

  4. Construction began

    Murphy International commenced works.

  5. Estuary signals went into operation
  6. Estuary timings adjusted

    Sequencing changed following initial delays.

  7. Bostik activation deferred

    An issue during final commissioning delayed activation. A revised date was still to be announced.

  8. Seatown commissioning week announced

    The works bulletin scheduled Seatown’s traffic lights for the week of 16 November.

  9. Seatown commissioning target revised

    The latest bulletin plans commissioning for the week of 23 November. OurSwords’ owner also reported the signals beside Bostik operating; their exact activation date was not established.

The wider purpose

Beyond the roundabouts

  • Walking & wheeling
    New pedestrian infrastructure and crossings along the corridor.
  • Cycling
    Dedicated cycle infrastructure and junction crossing points.
  • Public transport
    Designated bus lanes form part of the planned carriageway changes.
  • Connections
    The scheme runs east of Swords town centre, from the Pinnock Hill area towards Estuary.

When will it finish?

The published programme allows about 25 months of construction from April 2026, pointing to completion in 2028.

Make it useful

Plan around the works

For the wider local picture, open our Swords roadworks and traffic map.

Old Seatown Road: routes in the November traffic leaflet

Fingal’s November leaflet sets out changed journeys for the Seatown junction conversion, with the direct southbound exit from Old Seatown Road and the former U-turn route north no longer available under the new arrangement.

  • Going north: head east along Old Seatown Road, turn left onto Estuary Road, then left at the T-junction onto Spittal Hill. Continue past Fingallians to join the R132 northbound at the Estuary traffic lights.
  • Going south: head east along Old Seatown Road, turn right onto Estuary Road and continue to the IDA roundabout. Take the second exit onto Seatown Road towards the R132.

Open the council’s route map and November leaflet (PDF). The leaflet gives no separate start date for these restrictions; follow on-site signs as the junction changes are introduced. The existing programme targets the week of 23 November for Seatown’s signals.

Driving

Follow temporary signs and allow extra time when crossing the works. Familiar turns and lane arrangements may change.

Walking & cycling

Use the signed pedestrian routes and temporary crossings.

If you use a wheelchair, buggy or adapted cycle, check that the route suits your journey before setting off.

Taking the bus

Check your stop, direction and departure time before travelling. See our transport guide for journey-planning links.

Our Swords transport guide →

OurSwords coverage

More on the R132

All project coverage →

Useful questions

Common questions

Does “operational” mean finished?

The Estuary lights are operating, while finishing work continues around them.

What will change on this page next?

Look here for junction opening dates, changes to the works programme and new travel arrangements.

Spotted an error or a new notice?

Email [email protected] with the location, date and what you noticed.

Project backgroundThe R132 scheme, explained

Under construction · checked 20 November 2026. The scheme covers the R132 junctions and the routes between them.

What is being built?

The scheme covers roughly 3km of the R132 east of Swords town centre, from the Pinnock Hill area towards Estuary and Bostik. Its central changes include replacing the Estuary, Seatown and Malahide Road roundabouts with signal-controlled junctions, alongside dedicated walking, cycling and bus infrastructure.

Plans also include new crossings, turning areas and changes to the Drynam Road connection at Malahide Road.

Confirmed timeline

  • November 2020: public consultation began.
  • May 2021: detailed proposals were submitted for planning approval.
  • January 2022: planning approval was granted.
  • April 2026: Murphy International began construction.
  • 14 October 2026: the new Estuary traffic lights became operational.
  • 16 October 2026: signal timings at Estuary were adjusted following early delays.

20 November update: The council’s Seatown activation notice specifies vehicle signals from 10am on Monday 23 November, with walking and cycling crossings still closed. This is a planned activation, not confirmation that the junction is complete. Read the practical Seatown update.

Current works: bulletin covering 13–27 November

The 13–27 November bulletin plans Seatown’s traffic lights for the week of 23 November, alongside finishing works at Estuary and Seatown, cycle-track surfacing, and surfacing and footpaths at Chapel Lane.

Temporary single-lane sections may operate between 10am and 4pm during these works.

Bostik: the signals beside the factory were reported operating by OurSwords’ owner on 13 November.

What each junction means for your journey

Estuary: the lights are operating; finishing work and timing checks continue. Read the Estuary explainer.

Seatown: vehicle signals are scheduled for 10am on Monday 23 November. Walking and cycling crossings remain closed; use the Seatown Footbridge. The junction remains under construction.

Malahide Road: the roundabout conversion is included in the scheme; the circular layout remains visible in our 1 November photographs.

Completion target and open questions

The published programme points to about 25 months of construction from April 2026, taking the work into 2028.

Next milestones include Seatown’s signals and opening the new walking and cycling routes.

Change log — 25 October 2026: tracker established; 16–30 October bulletin added; Estuary commissioning and timing changes recorded.

Change log — 31 October 2026: current works refreshed to the 30 October–13 November bulletin; planned Seatown commissioning week and Bostik deferral added. Previous versions remain in the editorial record.

Photo update · 1 November 2026: AI reconstruction replaced with original OurSwords.ie photography; Estuary, Seatown and Malahide Road/Pavilions views added. © OurSwords.ie. Reuse requires permission.

Worth sharing?

Pass it on to someone in Swords.

FacebookWhatsApp

Local voices welcome

Have your say.

Log in to like · 0

Keep it kind, useful and local. Your first comment is reviewed before it appears. Community rules

0 Local conversation
Newest
Oldest Most Voted