OurSwords / Project watch
MetroLink.
Swords, connected.
Step by step.
The planned railway from Estuary to Charlemont, with four Swords-area stations and connections to Dublin Airport and the city.
Permission secured.
Procurement moving.
Detailed tendering is the current stage. Enabling works are planned from early 2027, with main works planned for 2028.
Order operativeProcurement
ActiveConstruction
PlannedPassenger service
Ahead

The immediate picture
What is happening now
Planning and delivery appointments
The Railway Order took effect on 12 January 2026. Jacobs AECOM joined as Programme Delivery Partner on 10 September, and Government approved detailed tendering on 16 September.
Preparing the route
Ground investigations have supported the design. Preparations for northern archaeological work cover Estuary to Fosterstown.
Main station and tunnel construction is still ahead.
Turning permission into contracts
Contracts cover the tunnels and stations separately from trains, railway systems and operation.
For Swords, the next changes to watch are contract awards, site preparation and local work notices.
The local route
Four stations. One Swords connection.
The four planned stations, from north to south.
Station order shown schematically; see the official route map in the sources.
Estuary
The northern terminus is planned with a 3,000-space Park & Ride. South of it, the alignment crosses the Broadmeadow and Ward rivers by viaduct.
Seatown
Planned in the Hertz Europe Service Centre grounds beside Seatown Road and the R132, serving north Swords and nearby workplaces.
Swords Central
The station beside the R132 is planned to connect with Pavilions, bus stops and the town centre through pedestrian links.
Fosterstown
Planned beside the R132, north of Airside Retail Park and close to Boróimhe. It is the southernmost of these four Swords-area stops.
The dated record
From approval to procurement
Select a milestone for the details.
Approval in principle
Government approved the initial business case, allowing the Railway Order application to proceed.
Railway Order application submitted
TII submitted the scheme’s planning application, including engineering and environmental proposals.
Oral hearing held
The application went through an oral hearing, followed by further public consultation later in 2024.
Ground investigation programme recorded
An official notice described borehole investigations for the design, mainly in Dublin city centre.
Railway Order granted
The planning authority notified TII that the Railway Order had been granted.
Mediation outcome announced
Following mediation, the project announced that Dartmouth Square West residents intended to withdraw their judicial review in January.
Railway Order became operative
The Railway Order took effect, authorising the railway works, specified land acquisition and operation.
Main civil-works contract notices launched
The M401 and M402 civil-works packages entered procurement. M402 covers Northwood to Estuary, including Swords.
Northern archaeology tender preparations
Five archaeology companies qualified to bid. The first tender scope covered Estuary to Fosterstown.
Utilities and enabling framework announced
The M14 framework entered procurement for site access, clearance, demolition and utility diversions.
Railway systems and airport packages progressed
The M500 contract notice covered trains, systems, fit-out and operation. On 29 May, procurement began for the M120 airport works framework, including the station box and portals.
Jacobs AECOM appointed
TII appointed Jacobs AECOM to support delivery management, engineering oversight, integration and commissioning.
Detailed tender stage approved
Government approved detailed bidding for construction and operation through Approval Gate 2.
The published programme
What comes next
Initial enabling works
Site preparation and utility diversions are planned from early 2027. Local notices will set out the affected streets and dates.
Detailed main-contract tender packs
Detailed M401, M402 and M500 tender documents are expected from the first quarter of 2027.
Bids inform the final business case
Bids are expected to give firmer costs in the second half of 2027, ahead of the final business case and Government decision at Approval Gate 3.
Main tunnelling and station construction
The September programme targets 2028 for the start of main tunnelling and station construction.
Testing, commissioning and passenger service
Testing and commissioning follow construction. A passenger opening date has not yet been confirmed in the checked programme.
What about the cost?
The September 2026 detailed business case gives a central estimate of €15.75 billion, within a €14.44–€17.49 billion range, including contingency and inflation but excluding VAT.
Tender bids and the final business case should provide a firmer cost.
Along the same corridor
Where the R132 fits
Road and crossing works
The R132 Connectivity Project changes junctions and walking, cycling and public-transport connections along the corridor. Its layout is coordinated with future MetroLink access.
New crossings are intended to be ready before MetroLink works remove the existing pedestrian bridges.
Open the R132 project tracker →Estuary roadworks
Estuary’s road signals began operating on 14 October 2026 and were adjusted on 16 October.
Those roadworks belong to the R132 project. Estuary metro station and its Park & Ride are separate works still ahead.
Read the Estuary junction report →OurSwords coverage
The story behind the milestones
Practical questions
What residents need to know
Can I plan a journey on MetroLink yet?
Not yet. MetroLink is planned to link Swords, the airport and the city. Use current bus services for journeys today.
Main Street buses →Will there be works outside my home?
Local work notices will identify the affected streets, dates and access arrangements. Check them before a journey or when work approaches your area.
How will this page stay useful?
We follow contract awards, local work starts and opening announcements. Send local observations to [email protected].
Sources & notes · checked 26 October 2026
Sources, dates & image credit
Official information checked 26 October 2026. Historical notices retain their original dates; future dates are programme targets. Contract notices, awards and site starts are separate steps. Phase bars show stages rather than measured percentages.
- Railway Order: grant, hearing and operative dates
30 September 2025 / 12 January 2026; hearing dates 19 February–28 March 2024 - Government approval and current construction programme
16 September 2026 - MetroLink detailed tender announcement
16 September 2026 - The Swords route and planned stations
Current route description checked 26 October 2026 - Programme Delivery Partner appointed
10 September 2026 - M400 and M500 procurement packages
Contract notices: February and May 2026 - Northern section archaeological procurement
24 March 2026 - Utilities and enabling framework
27 March 2026 - Airport works procurement
29 May 2026 - Resolution of judicial review
23 December 2025 - 2024 ground investigation notice
9 August 2024; historic investigation programme - Initial business-case approval
July 2022 - Railway Order application
30 September 2022 - How MetroLink will be delivered
17 September 2026 - MetroLink overview
17 September 2026
R132 junction dates: Fingal County Council’s 16 October 2026 update.
Photo: Ruwantha Wijesundara, Pexels photo 4070805, Pexels licence. Generic railway imagery, not a photograph of MetroLink. The station schematic is an original OurSwords design; official engineering drawings have not been reproduced.
Tracker established 26 October 2026. Next review listed for 2 November 2026.